Bengal Workers' Exodus Slows Construction in Trichy Ahead of Elections
Bengal Workers' Exodus Slows Trichy Construction

Trichy: A large-scale return of guest workers from West Bengal to vote in the state assembly elections has significantly slowed both government and private construction projects in the city, compelling contractors to depend on local labour.

Impact on Major Projects

Work has been affected for nearly two weeks at key sites, including the upcoming Kamarajar Grand Library at TVS Tollgate and the broad specialty block at MGMGH in Puthur. Officials stated that many workers employed through private agents left for their native places ahead of the two-phase polling on April 23 and 29.

"We have engaged local workers to keep the projects going. Full-fledged activity is expected to resume within a week after the guest workers return," a senior public works department (PWD) official said.

Wide Pickt banner — collaborative shopping lists app for Telegram, phone mockup with grocery list

Dependence on Migrant Labour

Contractors noted that the absence of workers from West Bengal, who constitute a major portion of the workforce in specialised tasks such as bar bending and shuttering, has delayed progress. "Nearly 80% of workers in bar bending are from Bengal. Their absence has slowed structural work. Agents indicate they may return by the first week of May," said S Prabhakaran, a civil engineer.

Local workers are largely engaged in masonry, while projects at the structural stage heavily rely on migrant labour. Some workers from Bihar and Jharkhand continue to be available, offering limited relief. Contractors added that most workers are likely to resume travel only after May 4.

The disruption has impacted not only major projects but also smaller residential constructions. "Higher wages and allowances demanded by local workers led us to depend on guest workers. While some projects continue with labour from Jharkhand, many have slowed," said contractor T Selvakumar.

Heat Affects Work Schedules

Meanwhile, rising temperatures have further affected work schedules. Labourers now start as early as 6 am, halt work during peak heat between 12 pm and 4 pm, and resume in the evening till about 7 pm, depending on site conditions.