Assam's Gauripur Bypass Project Faces Major Stalemate Over Technical Issues
In a significant setback for infrastructure development in Assam, work on the ambitious ₹318-crore Gauripur Bypass in Dhubri district has remained completely halted for more than two months. This prolonged stoppage has sparked widespread public anger and raised serious questions about the planning and execution of a project that was touted as a crucial step to alleviate urban congestion in the region.
Project Overview and Current Standstill
The 9.65-kilometer four-lane National Highway bypass, which was launched nearly two years ago, has drawn sharp criticism as progress has virtually come to a complete standstill. Sources within the National Highways Authority of India (NHAI) have revealed that the stoppage is directly linked to fundamental flaws in the Detailed Project Report (DPR). These flaws have led to complex technical complications that are now severely affecting construction activities on the ground.
The firm responsible for executing the project is reportedly in continuous touch with NHAI offices in both Guwahati and Delhi to clarify and address the DPR-related technical faults. However, industry insiders indicate that rectifying these issues is expected to substantially increase the overall project cost, adding another layer of complexity to an already troubled initiative.
Public Outcry and Local Concerns
Residents living along the proposed bypass stretch have expressed deep frustration and are demanding answers. "How did this project reach such a complete standstill, and who is ultimately responsible for these delays?" questioned local community members. They have unanimously called for immediate action: "If there are technical faults in the DPR or other issues, then they should be rectified promptly, and work should resume without any further delay."
Beyond the DPR issues, locals have raised alarming allegations about construction practices. They claim that poor-quality soil, fly ash, and other substandard materials have been used in this flood-prone area. With the onset of monsoon rains, early signs of erosion are already becoming visible, raising concerns about the long-term durability of the bypass once completed.
Structural Components and Progress Delays
The comprehensive bypass plan includes 42 culverts and three bridges, but progress on these critical structural elements has been minimal to non-existent. Particularly concerning is the construction of the bridge over the Khudimari Wetland, which has not yet commenced despite the project's official target completion date of October 2026.
An informed source close to the project revealed, "The bridge over Khudimari Wetland hasn't even started, and with the current standstill, meeting the 2026 deadline appears increasingly unlikely." This delay compounds existing worries about whether the project will deliver on its promised benefits within the planned timeframe.
Financial and Procedural Scrutiny
Adding to the project's troubles, concerns have emerged about potential financial irregularities under the Engineering, Procurement and Construction (EPC) model. Questions are being raised about whether the established EPC protocols are being properly followed, with some stakeholders suggesting the possibility of an investigation into the project's financial management and execution standards.
Official Response and Administrative Challenges
Syed Afroz Ahmed, Assistant Executive Engineer of NHAI (NH 17), provided some context when speaking to media outlets. He noted that he assumed his post in March this year, and the assembly election period followed shortly thereafter, potentially affecting administrative continuity. Ahmed confirmed that he had learned about anomalies in the DPR and that the matter was being processed at higher levels, including in Delhi.
"There are some issues concerning this Gauripur bypass, and these are being sorted out. Work will resume after completion and correction of anomalies in the DPR," Ahmed stated, offering assurance that resolution efforts are underway. However, he did not provide a specific timeline for when construction activities might recommence.
The prolonged halt of this significant infrastructure project highlights broader challenges in large-scale development initiatives in the region, particularly regarding technical planning, quality control, and project management oversight.



