Bombay High Court Directs MMRDA to Refund Rs 646 Crore Penalty to Reliance Industries
In a significant legal development, the Bombay High Court has ordered the Mumbai Metropolitan Region Development Authority (MMRDA) to refund a penalty of Rs 646 crore levied on Reliance Industries Limited (RIL). This penalty was imposed for an alleged seven-year delay in completing a convention and exhibition centre along with a commercial complex at the Bandra Kurla Complex (BKC) in Mumbai.
Court Sets Aside Demand Notices as Legally Unsustainable
The High Court, in a recent judgment, set aside two demand notices issued by MMRDA. The first notice, issued in 2017, demanded Rs 646 crore, while a second notice in 2019 sought an additional Rs 1,116 crore. The 2019 notice had been stayed by the court in 2020. The bench, comprising Chief Justice Shree Chandrashekhar and Justice Suman Shyam, delivered the verdict on April 8, declaring these notices as legally unsustainable.
The court strongly criticized MMRDA's actions, describing the collection of Rs 646 crore from RIL in February 2019 as "most arbitrary, high-handed, unfair, and unreasonable." It noted that this move subjected Reliance Industries to "undue pressure and threat of termination of lease, thus putting its business interest in peril."
Background of the BKC Project and Lease Agreement
The dispute traces back to December 2005 when MMRDA, as the owner of the BKC plot, invited bids for leasing 75,000 square metres to construct a convention centre. Reliance Industries emerged as the successful bidder in 2006. MMRDA approved the lease, requiring construction of 1,15,000 square metres within four years for a total premium of Rs 1,104 crore. The plot was leased for 80 years.
In 2007, MMRDA approved additional built-up area for the project, with RIL paying a premium of Rs 696 crore. MMRDA, represented by senior counsel Birendra Saraf, argued that it had rightfully invoked conditions under the 2006 lease deed, which stipulated completion within four years. However, senior counsel Vikram Nankani, representing RIL, contended that no time limit was set when granting the additional construction area, making the four-year deadline inapplicable.
Court's Ruling on Extension Clause and Penalty
The High Court agreed with RIL's arguments, ruling that "no additional premium or penalty was either payable or recoverable from RIL." It emphasized that MMRDA was duty-bound to apply a six-year extension clause to the project, similar to other projects. The court observed that a six-year extension policy granted by MMRDA for lease deeds executed after 2015 was "highly arbitrary and discriminatory," and its benefits should extend to RIL and three other cases where similar penalty demands were challenged.
The court directed MMRDA to refund the Rs 646 crore to Reliance Industries within 90 days. Failure to comply will result in interest charges. This decision underscores the importance of fair and consistent application of contractual terms in large-scale infrastructure projects.



